NEW YORK
FACT EXCHANGE
Menu

Menu

© 2026 NY Fact Exchange

Borough news

Manhattan · Morning

1:04

Published · Updated · New York time

East Village board backs two-phase rebuild at Tompkins Square Park

The proposed accessible mini-pool would hold about 66 swimmers, up from about 33.

Manhattan Community Board 3 backed NYC Parks’ proposal to rebuild the East Village park’s mini-pool, basketball courts and outdoor fitness area in two stages for about $9.93 million.

The first phase would cover the pool, courts and East 10th Street entrance. Parks estimates it would take about 15 months. The pool and courts would reopen before the fitness area closes for about nine months of work.

Parks has scanned and measured the existing exercise equipment. Once the agency selects the materials and dimensions for the replacement bars, the board wants it to present those details to the parks committee for comment.

Sources
Open Manhattan on the NYFE map · © OpenStreetMap

More from this edition

Explore